|
Watchgate Water Treatment Works, built in 1972, is North West Water's
largest water treatment plant with a maximum throughput of 700 Ml/day,.
Principally serving South Cumbria, Lancashire and Manchester. This equates
to over 30% of the total daily demand throughout NWW. The treatment process
is based on gravity filtration, with 456 - that is eight banks of seven
rows - rapid gravity filters designed by Manchester Corporation Waterworks.
The efficiency of the existing filters has fallen over the 27 years' continuous
service, leading to a marked increase in the required level of maintenance
and repair. NWW's Partnership Engineering Service Provider, Bechtel Water
Technology, manages the current filter refurbishment project.
A feature of the water treatment process is that the backwash cycle uses
treated water to carry out a high rate 'water only' filter backwash. The
uplift pressures imposed ion the filer floors during the backwash cycle
provide the worst case loading condition used for the structural design
of the floor system.
To maintain the highest possible operational throughput at all times;
an expedient solution to the refurbishment of the filter floors is required,
together with careful phasing of the construction works. The project also
includes the introduction of an air scour system to each filter and replacement
or refurbishment of associated control and isolation valves
|
|
(Fixing reinforcements for plinths) |
(Placing permanent formwork panels)
|
|
|
(Sealing around panels) |
(Backwash nozzles and reinforcement fixed, placing
concrete)
|
|
Existing Filter Construction |
|
The existing filters are of traditional plenum-floor construction,
in that filter media is supported on a perforated structural slab
- the plenum itself is the volume of the filter between the plenum
floor and the filter base slab, through which bother filtered and
backwash water pass as it exits and enters the filter, respectively.
It is theoretically possible, although in practice very difficult,
to enter the plenum to inspect the underside of the plenum floor,
its supports and the filter nozzles. The existing plenum floors are
pre-cast concrete panels into which are cast filter nozzles at close
centres. The panels are restrained by holding down bolts into perimeter
and central support walls, the joints between panels and between each
panel and the perimeter walls being sealed by a proprietary joint
sealant.
Investigations revealed that the floors had become unserviceable in
three ways:
- Media migrating through the joints between panels because of
the poor condition of the sealant, or via broken nozzles, resulting
in nozzles becoming blocked during backwash.
- Displacement of the panels themselves through failure of the
holding down bolts and support walls below. The condition of the
central support walls is such that they cannot be used to restrain
upward pressure on the plenum floor.
- The floors had become very sensitive to increases in pressure
above the current limitation of 6m head of water. This sensitivity
has affected operational versatility
|
|
To improve the efficiency of the backwash cycle, the new air scour
system will operate simultaneously with the water backwash. However,
to cope with potential seasonal algal blooms, the capacity of the
floors to cope with the full high-rate water wash had to be recovered.
This entailed replacing the existing plenum floors either with similar
precast concrete panel floors or with in-situ reinforced concrete
floors. Because of the problems experienced on the existing floors
with the central support walls and the floor sealing, an in-situ reinforced
concrete floor was preferred.
The floor system proposed by Morrison Construction Ltd and developed
by BCM Contracts Ltd is just such an in-situ reinforced concrete floor,
complete with intermediate supports and an arrangement of filter nozzles
suitable for both air and water backwashing.
BCM monolithic floors are a composite of preformed glass reinforced
cement (GRC) panels and in-situ reinforced concrete. In this application,
the lightweight GRC flat panels are rested on 160mm OD plastic piers
through which are fixed reinforcement anchor bars epoxy bonded into
the existing floor slab as shown in Figure 1.
The modular format GRC panels are laid on to the piers and existing
perimeter support walls to form a permanent GRC platform. A typical
installation will be made up of middle, edge and corner panels manufactured
to suit the installation. The panels are strong enough to support
men during concrete placing and lightweight enough to make handling
relatively easy.
Inevitably, with the number of panels in use, sealing of the joints
between panels and perimeter walls using mastic, tape or grout is
a critical activity before the concrete is placed over it. Figure
3 shows mastic sealing in progress.
A filter nozzle consists of a nozzle head and tail pipe. The nozzle
tail pipe is screwed into a pre-positioned bush in the GRC floor panel
and a disposable sealing cap is fitted to prevent ingress of concrete
while the floor is being cast. The structural reinforcement is laid
at uniform spacings between the tail pipes. Concrete is poured over
the GRC platform, filling the pier support tubes. It is spread until
level with the sealing caps, as in Figure 4. Special care is required
to ensure that each pier is sufficiently compacted, as there are no
sample, visible means of checking afterwards.
The nozzle tail pipe disposable sealing cap is removed and the filter
nozzle head screwed into position. The nozzle head incorporates narrow
slots, of the order of 0.2mm, which prevent filter material passing
through into the plenum chamber. The filter refurbishment is completed
by the addition of the filter media. |
Structural Design |
|
The plenum floor is designed as a suspended flat slab in accordance
with BS8110 and BS8007. Restraint against uplift forces is achieved
using pairs of tension anchor bars within each pier, epoxy bonded
to the existing chamber floor, and by keying-in around the perimeter
with dowels epoxy bonded into the walls of the filter chamber. The
use of pairs of bars in the piers, each with 200mm minimum embedment,
provides sufficient factors of safety to guarantee performance similar
to that normally expected of proprietary epoxy resin anchor systems.
Test anchors were employed to prove pull-out performance. Figure 5
shows the arrangement of the reinforcement. Benefits of using GRC
permanent formwork Typical benefits are:
- Largely jointless construction improves durability and reliability
resulting in reduced inspection and maintenance activities for
the client
- Accurate construction method employed to achieve the tolerances
required by the air scour system (± 3mm over 12m)
- Lower construction costs for the client, eg by avoiding the
use and removal of temporary staging under the floors
- Shorter construction period giving shorter outage and improved
security of supplies to the client
This article was prepared with assistance of the organisations involved
with the contract. It will be included as a Case Study in the Partners
in Technology report on The use of permanent formwork in construction,
part of a collaborative programme between CIRIA and the Concrete Society.
The report is being prepared under contract by Gifford and Partners.
|
|